Contacts

Technical inspection of buildings and structures, prices, estimates. Estimate for building inspection Inspection estimate

The cost of surveying buildings in most cases varies from 150 to 300 rubles per square meter. This article contains complete and detailed information on the cost of the survey and explains the basic principle of pricing, but if you need urgently And exactly determine the cost of surveying your property - click on the red button located to the right of this text and enter in the field that appears the minimum information about the property in any form - area, number of floors, purpose, your contact phone number or just email - and we will answer you immediately.

Cost of inspection of non-residential premises

When determining the cost of surveying a specific object, the customer is always faced with some variation in market prices. For a better understanding of its nature, choice optimal price And optimal performer It is useful for the customer to become familiar with the main factors influencing pricing when carrying out work to inspect buildings and monitor their technical condition.

The cost of the survey and the timing of the work are influenced by the following factors:

  1. Building area.
  2. Construction volume of the building.
  3. Complexity of constructive and space-planning solutions of the building.
  4. According to what project this building was built (according to an individual project or a standard project).
  5. Availability of technical reports on previous inspections of the building.
  6. Availability of design documentation for the building and as-built drawings.
  7. Completeness of the initial data provided by the customer.
  8. The complexity of the work (the need to pump out water, the need to carry out work at height, the number and depth of holes, etc.).
  9. The objectives of the survey (see the section below “Standard situations in which a survey is required”) and the resulting list of necessary work (scope of the survey).
  10. The workload of a specific design (research) organization at the time of work and the survey deadlines requested by the customer.
  11. Remoteness of the object.
  12. Other factors (additional customer requirements, mode of access to the site, etc.).

An efficient way to request a quote for survey work

To obtain a relevant result when requesting a quote from various organizations represented on the building survey market, the customer needs to:

  1. Form a request in the form of an email containing the minimum necessary information to calculate the cost, including the purpose of the survey, the area of ​​the building, other information from the above list of factors influencing the cost of the survey (if any), and also inform about the projects and documents available to the customer building being inspected.
  2. Scan and attach to the letter the necessary plans and documents that give an idea of ​​the size and features of the object.
  3. Send a letter with the same request to selected 10 -12 (or more) organizations.
  4. Receive commercial offers.
  5. Compare the commercial offers received, clarify details by phone or in subsequent letters, unclear questions regarding the prices, conditions and terms offered by the contractors.
  6. Select the optimal contractor.

The advantage of this method is that it gives objective price selection according to the market, since all participants receive the same requests. When calling design organizations by phone, the client runs the risk of receiving a biased spread of prices, since in each telephone conversation different details will be voiced (and understood) differently each time due to the effect called noise (or interference) in management science, which always occurs in oral communication . Each participant in the conversation can understand and interpret what they hear in their own way. In addition, the results of a telephone conversation are more difficult to confirm after some time at the stage of concluding a contract.

The main methods used in calculating the cost of work on the inspection of buildings and structures:

  1. A price determination method based on the calculation of actual costs of a design (research) organization.
  2. A method of comparison and extrapolation by area of ​​previously submitted commercial proposals.
  3. Calculation of the cost of work according to the prices recommended by federal and local regulatory reference books (calculation performed by this method, as a rule, gives a cost significantly higher than the two previous methods)

Price list used to calculate the cost of inspection of residential premises:

  1. Inspection of an apartment up to 100 sq.m. - 12,000 rub.
  2. Inspection of an apartment with an area of ​​more than 100 sq.m. - depending on the area and other parameters - as a rule, 20,000 - 25,000 rubles.

Price list used to calculate the cost of surveying non-residential premises (buildings) with a relatively small area:

  1. premises up to 50 square meters - 20,000 rubles.
  2. from 50 to 100 sq.m. - 25,000 rub. for the entire facility
  3. from 100 to 200 sq.m. - 35,000 rub. for the entire facility
  4. from 200 to 400 sq.m. - 200 rubles per 1 square meter
  5. from 400 to 700 sq.m. - 180 rubles per 1 square meter
  6. from 700 to 1000 sq.m. - 170 rubles per 1 square meter
  7. from 1000 to 1500 sq.m. - 160 rubles per 1 square meter
  8. Buildings with an area of ​​more than 1500 sq.m. - 150 rub. per 1 square meter with a decrease as the area of ​​the object increases. Due to the large area, the cost of survey work in some cases (same-type halls, hangars, large workshops) can drop to 100 - 50 rubles per square meter. In each specific case, the cost is calculated using one of the three methods above, depending on the 12 factors listed above.

Examples of commercial proposals for building inspections, giving an idea of ​​the possible cost of the work:

  1. Inspection of building structures of non-residential premises with an area of ​​366 sq.m. (Moscow) - 118,000 rubles/10 working days
  2. Inspection of building structures (load-bearing walls, floors) in non-residential areas. pom. area 125 sq.m. (Moscow) - 45,000 rubles/10 working days.
  3. Inspection of a premises with an area of ​​552 sq.m. in a non-residential building with technical preparation. conclusion on the admissibility and safety of the redevelopment carried out - 65,000 rubles / 7 working days.
  4. Inspection of the structures of the second lift pumping station building in Podolsk, Moscow region with the preparation of a technical report on the possibility of demolition. (area 189 sq.m., construction volume 1134 cubic meters) - 80,000 rubles/12 working days.
  5. Inspection and assessment of the technical condition of roof structures, identifying defects and issuing recommendations for their elimination for non-residential premises with an area of ​​734 sq.m. in Obninsk, Kaluga region - 150,000 rubles/15 workers. days.
  6. Inspection of the building foundations and the main load-bearing structures of the above-ground part of the building with an area of ​​800 sq.m. in the city of Dubna (M.O.) with the opening of 3 pits. Sampling of soils and determination of their physical and mechanical properties. Establishment of emergency areas. Issue of a technical report on the condition of the building's building structures. Preparation of recommendations for carrying out measures for the further safe operation of the building, including the installation of a ventilated facade - 155,000 rubles / 15 workers. days.
  7. Inspection of building structures with the preparation of a technical report on the possibility of converting part of the building into a washing complex (100 sq.m.), Odintsovo district, Moscow region - 80,000 rubles/7 workers. days.
  8. Inspection of a commercial building with an area of ​​121 sq.m. in Moscow with the preparation of a technical report on the safety and admissibility of the previously completed redevelopment - 150,000 rubles / 10 workers. days.
  9. Inspection of the building of the cultural center with checking the load-bearing capacity of the floors, load-bearing columns and strength characteristics of materials with the issuance of recommendations for the restoration of defective structures of the entrance group before redevelopment and major repairs of the building (area 2000 sq. meters, Moscow) - 160,000 rubles / 12 working days.
  10. Inspection of the load-bearing structures of the building for the installation of a ventilated facade with the issuance of a technical report on the condition of the load-bearing structures in connection with the installation of a ventilated facade of the building with recommendations for further operation in Moscow - the area of ​​the inspected building is 6400 sq.m. - the cost of the examination is 280,000 rubles, the period for completing the work is 15 working days.
  11. Inspection of building structures of part of the floor of a building in Podolsk, M.O. with an area of ​​2700 sq.m. regarding the possibility of reconstructing part of the floor of the building for the placement of heavy equipment - 280,000 rubles / 12 working days.
  12. Inspection of building structures and foundations of part of a building with an area of ​​700 sq.m. in Moscow - 330,000 rubles/12 workers. days.
  13. Carrying out a complex of survey and design work in Tver for a building with an area of ​​180 sq. m. m. with an inspection of building structures, measurement work and the development of the KR section (structural solutions) for the installation of a fire tank - 290,000 rubles, 15 working days.
  14. Inspection of a non-residential building with an area of ​​6000 sq.m. in Smolensk for the purpose of reconstruction (foundations, walls, load-bearing structures of floors, columns) with a conclusion on the possibility of reconstruction of the building - 950,000 rubles / 30 workers. days
  15. Inspection of the public and business center building with an area of ​​5000 sq.m. in Kotelniki, Moscow region. The survey area is 836 square meters. Inspection of the building's load-bearing structures (bearing structures of the sixth floor: pylons, ceilings and selectively balconies, canopies), including determination of the strength of reinforced concrete structures - 315,000 rubles, 14 working days.
Building survey- a set of measures carried out to identify the technical condition of the building and its building structures.

In the process of work, data is collected, which is analyzed and used to develop solutions to eliminate defects, strengthen structures and foundations of buildings.

As a result of the inspection, a document is generated - (inspection report), which is issued to the customer.

The inspection department of the StroyKomplekt group of companies is able to carry out inspections of buildings in a short time and at reasonable prices.
Our experience allows us to do our work better, faster and cheaper.

Quick navigation through the article

Why you should entrust a building inspection to us:

  • We are not intermediaries and carry out absolutely all work using our own specialists.
  • Our reputation and long-term partnerships are important to us, so we work for results.
  • We do not miss deadlines and also fulfill urgent orders.
  • A specialist’s visit to your site and consultation are free.
  • We have been providing a full range of services for the inspection of buildings and structures since 2006.
  • We examined 389 objects, a total of 8 million cubic meters (as of July 2016).
  • The technical conclusions we issue as a result of the examination have legal force, are as accurate, accurate and competent as possible.
  • We have all the necessary permits and licenses to conduct survey work, including SRO permits to hazardous facilities of level 1A.
  • At each stage of the survey, we provide a report on the work done and the results obtained.
  • All devices we use are certified and tested by Rosstandat.
  • Our estimates are absolutely transparent and do not contain anything “extra”. If you provide us with information about the object, we will be able to calculate the exact time frame and announce the exact amount, and you will pay only that and not a penny more.

391 5191

Inspection of buildings and structures is carried out in the following cases:

  • when defects and damage occur in structures
  • when buying and selling
  • when restoring design or as-built documentation
  • if you need to find out what condition the building is in.
  • before major repairs, reconstruction, technical re-equipment (during modernization)
  • it is necessary to identify deviations from the executive and design documentation of the building
  • quality control of work performed by the contractor at your site.
  • acceptance into operation of a new building. Inspection of buildings will reveal poor quality work
  • clarification of the cost of work performed and building materials used, as well as their compliance with Russian building codes and standards
  • if a dispute arises between the contractor and the customer regarding the quality of construction
  • allows you to assess damage caused by improper operation, fire, design errors

Comprehensive inspection of an administrative building, Central Administrative District, Moscow

Cost of building inspection

The minimum cost of the examination is from 50 thousand rubles.

To clarify the cost of the survey for your property, we recommend contacting us by phone or email, which are listed on the website, or use the calculator below.

To calculate the cost of work on inspection of buildings and structures current collections of base prices are used, using the inflation index for design work. The price depends on many factors, including the area of ​​the building, design features, etc.

Building Survey Cost Calculator

To ask a question or request a building inspection,
call us on +7 499 391 5191
or contact us by email info@site

Time frame for building inspection

Like the cost, the timing of the survey work depends on the current characteristics of the building, its volume, number of floors and many other parameters. If we consider "average" inspection”, then the period of work will be two weeks; for your object this figure may differ, but usually the time frame rarely goes beyond this. The minimum period for which we conducted the survey, including collecting all documentation and drawing up a technical report, is 24 hours. You can find out the exact timing and cost of the work if you contact us by phone or email.

The result of the examination

The result of the building inspection work is a certificate issued to the customer technical conclusion, which defines the category of technical condition of the research object. A technical report is an official document that has legal force.

The technical report contains conclusions and recommendations for the further operation of the building, recommendations for restoring the load-bearing capacity of building structures and materials justifying the technical decisions taken. The technical report also shows the design features of the structure as a whole and its structures.

The survey results are also presented in the form inspection report, when a small volume is examined or when only a separate structure is examined.

Composition of the technical report

  1. Examination program
  2. Photo recording
  3. Defect sheets and defect cards
  4. Graphic materials
  5. Foundation research materials
  6. Protocols for studying the strength characteristics of materials
  7. Protocols of openings of building structures
  8. Geodetic survey of building structures
  9. Verification calculations

You can familiarize yourself with the composition of the technical report in more detail

Inspection of the administrative building on Academician Korolev, Moscow

To ask a question or request a building inspection,
call us on +7 499 391 5191
or contact us by email info@site

  • You receive a detailed report describing the current state of the structures, the methods used to conduct the survey, calculations and recommendations for operation, major repairs or reconstruction of the building.
Cost calculator for construction expertise, inspection of building structures
Select building type

Retail buildings Retail MFC Administrative Industrial Warehouse MFC Residential buildings

M2:

Important!
Cost calculation
from 10,999 m2 or 31,892 m3
Settlement and explanatory note0 0
Analysis of as-built documentation, preparation of a list of defects, photographic recording of the subject of examination0 0
Inspection of building structures - determination and assessment of actual values ​​of controlled parameters:
1. Columns, pilasters;
2. Walls;
3. Partitions;
4. Load-bearing elements of the coating;
0 0
5. Foundation;0 0
6. Roof;0 0
7. Floors.0 0
Carrying out a verification calculation based on the survey results0 0
Power supply system, photographic recording0 0
Water supply system, photographic recording0 0
Drainage system, photographic recording0 0
Heating, ventilation and air conditioning, heating networks, photographic recording0 0
Communication networks, photographic recording0 0
Gas supply, photographic recording0 0
Thermal engineering calculation of external enclosing structures0 0
Measuring the strength of concrete using the ultrasonic method0 0
Performs opening of structures, sampling of concrete, determination of composition and reinforcement0 0
Inspection of foundations in open pits0 0
Development of building plans in PDF format based on BTI0 0
Photography of building facades, development of facade drawings0 0
Development of plans for the placement of elements of the internal engineering systems of the building (risers VK, OV, placement of ASU, placement of utility inputs)0 0
Determination of geological conditions of the construction site (properties of foundation soils)0 0

Building survey

The owner of the building is directly interested in its long-term operation. This encourages him to carry out periodic inspections and surveys of the structure.

GOST R 31937-2011 determines when it is necessary to conduct an inspection of a building or structure. There are the following types of work of this type:

  1. regular;
  2. warning;
  3. voluntary.

The former are carried out in accordance with the requirements of regulatory documentation, the latter are carried out when there is reason to believe that there is a need for repair and restoration work. The third type of work is performed based on the wishes of the owner of the structure.

Procedure for conducting the examination

The building inspection is carried out in several stages:

  1. Familiarization with project documentation.
  2. Visual inspection.
  3. Examination using special equipment and tools.
  4. Processing of received information. Analysis of identified problems and defects.
  5. Development of proposals for the further use of the structure, and strengthening of building elements and the entire building.
Cost of building inspection in thousand rubles.
m2* Visual Instrumental Superstructure,
Extension
up to 500105 120 320
600 105 130 330
700 105 140 340
800 105 150 350
1000 105 170 360
1200 110 190 370
1400 115 210 380
1800 120 250 390
2200 125 290 400
2600 130 330 410
3000 135 370 420
4000 140 470 520
5000 150 570 620
Cost of preparing a defective statement
Additional work
The cost of a building inspection is additional. work in thousand rubles
m2 Opening of structures without backfilling and sinking 1 m3 of pit Measurement work Thermal engineering calculation for repair design
up to 50045 40 35
600 45 45 35
700 45 50 35
800 45 55 40
1000 45 60 45
1200 55 70 50
1400 60 80 60
1800 70 100 70
2200 70 120 80
2600 80 160 90
3000 90 200 100
4000 100 300 150
5000 110 400 200

After the building has been inspected, an expert opinion is drawn up. The building inspection includes a comprehensive assessment of the condition of walls, interfloor ceilings, door and window blocks, load-bearing structures, foundation, columns, beams, trusses, etc.

The cost of conducting an inspection of buildings and structures depends on their area.

In case of non-standard situations and building features, the cost of work may increase. The cost increases when additional work is carried out: opening structures, measurements. It is possible to carry out calculations of heat loss inside the building.

In accordance with SNIP standards, structures and buildings must periodically undergo assessment of their current condition. All research is carried out by specialized enterprises. The work assignment is developed by the customer with the participation of the survey performer.

Cost of building inspection

Prices vary depending on the task:

  1. a planned, extraordinary or after an emergency assessment of the wear of structures is required;
  2. redevelopment or major renovation of the building is planned;
  3. unfinished construction is resumed or documentation for “self-construction” is created;
  4. to determine the causes of deformation of structural elements.
  5. Drawing up an official conclusion for the examination involves performing work in three stages:
  6. preparation of documentation, visual familiarization with the object and performance of work with drawing up a conclusion.

The first stage is the preparation of design and technical documentation for this structure, i.e. “familiarization with the object of inspection.” Then a schedule and list of works are drawn up based on the technical specifications.

The next stage is an inspection of the object in order to detect visible defects and flaws.

The third stage of the survey is carried out directly at the site using tools:

  • the geometry of buildings or structures, as well as their parts, is checked;
  • using technical means, the properties of damage and flaws are determined;
  • the actual strength of the materials of the main supporting structures is checked;
  • environmental parameters characteristic of the life activity of a given object are measured;
  • real operational loads on the structures being examined are checked, taking into account changes in the soil base;
  • the existing structural solution of the building and its individual elements is determined;
  • the actual forces of the main (bearing) blocks, which bear the main loads, are calculated and the real load-bearing capacity of the building and its main structures is determined;
  • The laboratory tests samples of materials of the building being inspected.
Technical inspection of buildings and structures, prices are flexible

Inspection of buildings and structures allows for timely identification of damage and critical conditions of structures. The survey ends with the drawing up of an official technical report, which provides detailed recommendations on the possibility of operating the building. The final summary of the technical report is a list of measures recommended by the survey contractor to strengthen structures, eliminate detected defects and the reasons for their occurrence.

Estimate for building inspection
to carry out the work "Inspection of the technical condition of building structures of the building located at the address: St. Petersburg, Mezhevoy Canal, building 5, lit. A.

Technical characteristics of the building:
building height - 33.33 m;
basement height - 2.7 m;
building area - 1692 m2;
construction volume of the building is 56394.37 m3.

Estimate for carrying out measuring work

Name of works

Number of works and costs

Unit cost measurements, rub.

Total cost, rub.

Foundation plans and footings

Floor plans of the building

Floor plans with determination of floor composition

Transverse and longitudinal sections with joints of structures

Facades, windows, gates

Stairs

Plans for floor structures with openings

Roof plans with openings


(Table 10 p. 1) - 1.2

(Table 10 p. 10) - 1.2

Pre-contractual work (clause 2.13) - 6%

Total estimate:

30515.9

Estimate for survey work

No. p/ P

Name of works

Unit change

Number of works and costs

Unit cost measurements, rub.

Total cost, rub.

Foundations

Walls, partitions, lintels, windows, doors

Stairs

Floors

Combined coatings

Taking into account working conditions factors:
(Table 10 p. 1) - 1.2

(Table 10 p. 10) - 1.2

Taking into account the coefficient for the volume of the building (clause 2.7 of Table 11) - 1.8

Pre-contractual work (clause 2.13) - 8%

Total estimate:

54561.96

The estimate was compiled on the basis of the "Handbook of basic prices for measuring work and inspections of buildings and structures" MOSCOW 1998.

Estimate for sampling and testing of building materials

No.

Name of works

Unit change

Price per one. change, rub.

Physical and mechanical testing of foundation concrete:

a) sampling from structures

1 sample

b) cutting out a cube of the correct shape with inspection and description of the type of filler:

c) a cube with dimensions 10?10?10 cm

d) inspection of the structure and drilling of the core with trimming of planes

d) sample testing and processing

Physical and mechanical testing of bricks:

a) external inspection of the facility and determination of brick sampling locations

b) selection of bricks from the masonry body

c) external examination

d) determination of volumetric weight

e) sample preparation and compression test

f) sample preparation and bending test

g) processing of test results

Determination of the physical characteristics of roofing materials:

a) opening the roof with sampling (roofing, insulation)

b) weighing the roof components

c) determination of the moisture content of the components

d) processing of autopsy results

Total estimate for one sample:

for concrete

for brick

for roofing materials

Required number of samples:

for concrete - 10 pcs.

for brick - 10 pcs.

for roofing materials - 4 places

486.86

Including delivery to the site: - 486.86? 0.15

Total estimate:

559.889

The estimate was compiled on the basis of the "Handbook of basic prices for measuring work and inspections of buildings and structures" MOSCOW 1998.

Estimate for technical leveling of the base (II class)


p/p

Name of works

Unit change

Number of works and costs

Price per one. Measurement, rub

Total cost, rub.

Reconnaissance of locations for leveling and slats

1 station

20 stations

Leveling class II

1 x double travel tripod

20 station

10,2
9,2

204,0
184,0

Total estimate:

528.0

The estimate was compiled on the basis of the "Handbook of basic prices for engineering and geodetic surveys during the construction and operation of buildings and structures" MOSCOW 1999.

Estimate for excavation of the building

Scope of work:
- drawing up plans, sections indicating the location of the pits;
- control over the autopsy;
- production of measurements.
Table 19

To carry out work to establish the condition and type of foundations, it is necessary to carry out excavation holes under all load-bearing walls of the building, at least 4 holes.
Total estimate: 26 rub..
The estimate was compiled on the basis of the "Handbook of basic prices for design work on inspection, assessment of technical condition, testing and strengthening of building structures of buildings, structures, cranes and elevators." 2nd edition, revised and expanded.

Summary estimate


p/p

Name of works

price, rub.

Carrying out measuring work

30515.9

Carrying out survey work

54561.96

Sampling and testing of building materials

313.230

Carrying out technical leveling of the base

97.0

Execution of pits for foundation inspection

26 rub.

Total estimate:

Building survey- this is a specific list of operations, the purpose of which is to check the condition and defects of both the buildings themselves and any of its structural elements.

There are several main objectives of the survey:

  1. Inspection and research before putting buildings into operation;

The main task is to check the compliance of the constructed building with the design documentation, as well as to identify violations.

  1. Inspection and research of buildings that have already been built.

Determining the deterioration of the building, the possible load-bearing structure of the building elements, taking parameters for the reconstruction of the building. Scheduled and unscheduled inspections.

  1. Various laboratory tests of structural elements;

There are basic requirements for buildings and structures that must not be violated:

  1. All buildings and structures must be strong and stable.
  2. Lagging behind the building are cracks and damage.

All other deviations from the normal state of objects should be examined by trained engineers with experience working on the relevant objects and having specialized equipment available.

Any examination consists of several elements:

  1. Primary. Study of design documentation, familiarization with the repair work carried out.

In this case, it is possible to determine the weak areas of the design schemes, as well as the places of maximum load and the theoretical degree of wear.

  1. Visual inspection. The engineer studies the object’s compliance with the working documentation, searches for defects, and draws up a plan for a more detailed examination. All surveys are carried out using non-destructive methods.

Important. Non-destructive methods are any types of examinations that do not require direct disabling of operating objects, without physical sampling of materials.

The visual examination includes:

  • Carrying out measurements of the property and subsequent production.
  • Drawing up a list of defects with photographic recording.
  • Assessing the reliability of building elements.

Upon completion of the visual inspection, the customer is provided with

  • List of defects, with a description of their nature, location on the diagrams;
  • Photo recording with the class and characteristics of defects;
  • Description of possible deformations of the building or its individual elements (deflections, tilts, bends, distortions, faults, etc.);
  • Identification of emergency areas;
  • Updating and sectional diagrams of the building;
  • Determination of load-bearing walls and structures with location on the drawings;
  • Preliminary analysis of the condition of load-bearing structures and utility networks;
  • Recommendations, estimates for eliminating identified deviations;
  1. Full analysis with testing of structural elements and development of possible ways to solve the problems.

Determination of the design features of a part of the building, assessment of the technical condition of the load-bearing and enclosing structures of the building to calculate the loads on the floors. Structural elements are subject to technical inspection: foundations, floors, walls.

Scope of services in case of full technical inspection:

  1. List of works when inspecting base soils and foundations with
  2. digging 4 pits for the building:
  3. Analysis of engineering and geological conditions of the site (land under the building);
  4. Carrying out research pits to clarify parameters
  5. foundation;
  6. Selection of soil samples from under the foundation soles to clarify properties
  7. soils;
  8. Performing laboratory tests of foundation soils.
  9. Foundation material testing;
  10. Dynamic sensing to a certain depth (depending on the size and height of the building);
  11. Carrying out verification calculations to determine the design resistance and maximum ground pressure.
  12. Inspection of the technical condition of engineering networks.
  13. Installation of deformation marks on the main structures of the building. (average 20 pieces)
  14. Installation of geodetic marks
  15. Leveling class II (building settlements) (depending on the number of corners of the building)

List of works during visual and instrumental examination of the above-ground part of the building:

  1. Inspection of the technical condition of the building.
  2. Inspection of building structures with sketches of defects and damage, photographic recording of defects and preparation of a defect list;
  3. Determination of the strength of walls using non-destructive methods;
  4. Carrying out openings of floors to clarify its composition and
  5. determination of bearing capacity.
  6. Sampling from structures for mycological studies - the number of samples for the laboratory is specified based on the results of autopsies.
  7. Measurement work required for the survey
  8. Analysis of archival materials.
  9. Necessary calculations of load-bearing structures (floors, walls).
  10. Determination of the building category based on the technical condition of structures according to TSN 50-302-204, GOST R53778-2010.

Sample estimate for building inspection

The estimate is compiled in prices for the third quarter of 2015. Prices are given per 100 m3 of building.

The estimate was compiled on the basis of the Directory of basic prices for measurement work and inspection of buildings and structures, State Enterprise "Tsentrinvestproekt", M., 1998.

The total volume of the building is 74,940 sq. m. m.

Sample terms of reference(for drawing up tender documentation):

In case of visual inspection:

Option 1

Technical task

  1. Place, conditions and timing of work

1.1. Place of work: __________________________

1.2. Turnaround time: __________________________

1.3. The Contractor is obliged to carry out a visual inspection of the main load-bearing structures of the building with photographic recording, drawing up a report with conclusions and recommendations, developing statements and diagrams of defects in a non-residential building at the address: st. Millionnaya 30 lit.A.

1.4. Main technical and economic indicators of the building being examined:

Year of construction – _____, capital year. repair – _____

Total area - ____

Purpose – __________________

2. Requirements for the description of work performed

2.1. Name of work performed: Conducting a visual inspection of the main load-bearing structures of a non-residential building in accordance with the requirements of GOST 31937-2011.

2.2. Requirements for the work performed:

2.2.1. An organization that meets the requirements for design organizations established by the legislation of the Russian Federation and has a valid Certificate of Admission to perform this type of work is allowed to carry out work.

2.2.2. The Contractor transfers to the Customer the design documentation developed by him in 3 copies on paper and 1 copy on electronic media.

2.3. List of structures inspected and scope of work:

2.3.1. Inspection of concrete and reinforced concrete structures (according to clause 5.3.1. and appendix E GOST, without opening)

2.3.2. Inspection of stone structures ( without opening or probing)

2.3.3. Inspection of steel structures (according to clause 5.3.3 and appendix Zh GOST, without opening)

2.3.4. Inspection of wooden structures (clause 5.3.4., without opening or drilling)

2.3.5. Inspection of building elements of balconies, bay windows, loggias - clause 5.3.5., without opening

2.3.6. Inspection of stairs - clause 5.3.5. without opening

2.4. The result of the visual inspection is the development of a report on the technical condition of the main load-bearing structures of the building with:

— indicating the structural diagram of the building and describing the load-bearing structures of the building by floor;

— compiling lists of defects and damage based on external signs with their measurements and recording on diagrams;

— description of emergency areas (if any);

— developing conclusions about the condition of the building;

After conducting an inspection of the technical condition of the building, the information in the developed report should be sufficient to make an informed decision about the possibility of its further trouble-free operation.

The report is transferred to the Customer according to the Acceptance Certificate.

Sample technical specification Option 2

Technical task

Price guide for inspection of buildings and structures

Directory of basic prices for measurement work and inspection of buildings and structures, State Enterprise "Tsentrinvestproekt", M., 1998.

The final cost of the work is determined using the coefficient approved in a letter from the Russian Ministry of Construction. The latest version of the letter and the required coefficient can be found on the Internet.

Result of technical inspection of buildings and structures

In a request for a commercial proposal, we only need a few characteristics: Address of the property, area of ​​the property, number of floors, as well as the required type of survey.



Did you like the article? Share it